Soft film ceiling construction steps

Soft film ceiling construction steps Before installing smallpox, check carefully whether the keel joints are firm and smooth. Stick the white tape on the sprinkler head. When installing smallpox, firstly fix it from the middle to both sides, and pay attention to the dimensions of both sides. Note that the welding seam must be straight and do the angular position first. Pay attention to smoothness. After all the work is done, trim the excess ceilings. To achieve a perfect edge effect.

1, soft film ceiling construction personnel to the site to see if there is a condition to install the keel: that is, to see whether the wall is completed on the scene, woodworking part of the processing is qualified, you need to first complete the plaster part. Special attention should be paid to the woodworking part in accordance with the requirements we have proposed, and the size of the openings such as lamps and tuyere should be processed in advance.

2. When the site conditions permits the parties to enter the site, the first step is to fix the aluminum keel keel according to the requirements of the drawings. The corners must be flat and smooth, and the connections must be flat and dense.

3, pay attention to the lighthouse, tuyere, light pipe plate and the surrounding keel level, and require solid and stable can not swing.

4, smoke, ceiling lamp, first position and then do a wooden chassis, the bottom of the wooden chassis to be polished smooth, and pay attention to the level, too low it is easy to highlight the traces of the chassis.

5, before installing smallpox, carefully check the keel joint is firm and smooth, sprinkler head to stick white tape, air outlet to be handled well. When installing smallpox, firstly fix it from the middle to both sides, and pay attention to the dimensions of both sides. Note that the welding seam must be straight and do the angular position first. Pay attention to smoothness. After all the work is done, trim the excess ceilings. To achieve a perfect edge effect.

6. Open the lamp hole: Make a mark on the position of the lamp hole, carefully stick the PVC lamp ring to the bottom of the soft film, and remove the extra smallpox after it is firm.

7, open mouth, light tube Handicap: Find the position of the light pipe tray, with the same as the surrounding, the soft film is installed on the aluminum alloy keel, pay attention to the angle to be flat. After doing a good job, you can remove more of the smallpox.

8. Finally, clean the soft film ceiling surface with a clean towel.

installation steps:

step one:

1. According to the design requirements of the drawings, a 4X4Cm support keel (which can be a square or square steel pipe) is fixed around the horizontal height of the soft film ceiling. . Note: In some areas, large blocks are required for installation in order to achieve good results. This requires a wood strip in the middle. This is actually handled according to the actual situation.

2. When all the wood strips need to be fixed, then install the aluminum keel of the soft film ceiling on the bottom of the supporting keel. (See the design drawings for details)

Step two:

1. When all aluminum alloy keels installed with soft film ceiling are fixed, install soft film. First, the soft film is opened and heated with a special heating air gun. Then, the soft film is tensioned and inserted into the aluminum alloy keel with a special insert knife. Finally, the soft film around the film can be trimmed completely. (See details of construction design drawings)

2, after installation, use a clean towel to clean the soft membrane ceiling.